Derrick crane 7 t / 4,25 m + 3,2 t / 3,5 m

PROJECT NAME: Derrick crane 7 t / 4,25 m + 3,2 t / 3,5 m

 

INVESTOR: Fishing trade – own. Branimir Gvačić

 

LOCATION: Rab

 

YEAR OF PRODUCTION: 2012.

 

TTECHNICAL CHARACTERISTICS:

                                                           main console                 auxiliary console

  • maximum capacity:                                     7 t                                       3,2 t
  • maximum reach:                                         4,25 m                                 3,5 m
  • lifting height:                                               9,65 m                                 9,5 m
  • lifting speed:                                         4,2/0,42 m/min                         5/0,5 m/min
  • rotation speed:                                            0,1 rpm                               0,27 rpm
  • angle of rotation:                                         140 deg                               110 deg

 

TECHNICAL DESCRIPTION:

At the request of the investor, the fishing trade - owned by Branimir Gvačić, the derrick crane was reconstructed and upgraded with the addition of second console, in addition to the existing one, where the derrick crane now has a main and auxiliary console. The crane is mounted on the existing foundation on the operational shore where the vessel is being lifted, on which a derrick crane with one console with a load capacity of 3,2 t was previously located.

 

The main bracket has a nominal load capacity of 7 t, a hook reach of 4,25 m and a lifting height of 9,65 m. The auxiliary bracket, pre-assembled, has a nominal load capacity of 3,2 t, a hook reach of 3,5 m and a lifting height of 9,5 m. auxiliary console is mounted pre-existing drive.

 

All working movements of the crane: lifting / lowering the vessel and rotation of the consoles are electrically driven.

 

The purpose of the crane is to lift / lower the vessel from/into the sea and place it on a transport trolley, vehicle or deck chair.

 

The steel construction of the crane basically consists of:

  • load-bearing column,
  • two consoles with clamps (main and auxiliary),
  • service platform and climbers.

 

The electrical equipment of the crane consists of:

  • two electric motors of the main lifting mechanism,
  • electric motor auxiliary lifting mechanism,
  • electric motor of the rotation mechanism of the main console,
  • electric motor of the rotation mechanism of the auxiliary console,
  • control cabinet,
  • radio remote control and suspended cable control unit (as reserve),
  • main switches, and
  • power and control cables within the crane itself.